BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.
For more information on roadwork in the City of Bloomington, visit www.bloomingtonstreets.com, e-mail engineer@cityblm.org or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.
FY26 resurfacing
E. Oakland Ave, west of Prospect through Hershey
- A final inspection has been completed and cleanup will be scheduled.
People are also reading…
Prospect Rd, Oakland to Empire
- A final inspection has been completed and cleanup will be scheduled.
E. Washington St, Veterans through Hershey
- A final inspection has been completed and cleanup will be scheduled.
FY27 resurfacing
Eastland Dr, Fairway to Hershey
Stage 1: Veterans to Hershey
- Installation of the asphalt surface course has been completed.
- Installation of pavement striping has been completed.
Stage 2: Fairway to Veterans
- Installation of the asphalt surface course has been completed.
- Installation of pavement striping has been tentatively scheduled.
Four Seasons Rd, north of Oakland through the cul-de-sac
- Installation of the asphalt surface has been completed.
- Completion of pavement striping has been rescheduled.
St. Joseph Dr, Washington to Eastland
- Installation of the asphalt surface has been completed.
- Installation of pavement striping has been completed.
N. Hershey Rd, north of Lamon through Jumer
Stage 1: Jumer to Rainbow (concrete pavement)
- The limits and layout of the work zone has been completed.
- Underground utility (JULIE) locations have been requested.
- Installation and adjustment of the traffic control devices is in progress.
- Removal and replacement of the underground utility work has been completed.
- Removal and replacement of the concrete items (curb and gutter) has been completed.
- Removal of the underground utility castings (manholes and water valves) has been completed.
- Removal (milling) of the concrete surface has been completed.
- Removal and replacement of the concrete patches have been completed.
- Joint/crack repairs have been completed.
- Installation of the asphalt (sand) binder course has been scheduled for November 3.
- Installation of the longitudinal joint sealant and prime coat for asphalt surface will be after the completion of the asphalt binder course.
- Installation of the asphalt surface course has been tentatively scheduled.
Stage 2: Rainbow to Lamon (asphalt pavement)
- The limits and layout of the work zone have been completed.
- Underground utility (JULIE) locations have been requested.
- Resurfacing of this section of Hershey has been temporarily suspended until spring 2027.